Shared Flashcard Set

Details

CSI CDT: Module 1:
Introduction to Project Delivery
22
Architecture
Professional
10/08/2012

Additional Architecture Flashcards

 


 

Cards

Term
What are the 4 project teams?
Definition
Owner, Design, Contractor and Supplier
Term
Describe the role of the Owner.
Definition
Establishes the design requirements, budget, and time constraints for the project. As the ultimate purchaser of installed products, the owner may have significant input on equipment and finish selections and may require information on product operation, maintenance, and warranties. (PDPG 2.2)
Term
What are Instruments of Service?
Definition
The work product of architects and engineers that includes a seal attached to the documents. (PDPG 2.3)
Term
List the 8 stages of a facilities life cycle.
Definition
 Project conception
 Project delivery methods
 Design
 Construction documents
 Bidding/negotiating/purchasing (procurement)  Construction
 Facility management
Deconstruction/Demolition
(PDPG 3.4)
Term
What is accomplished during the Project Conception Phase?
Definition
an owner’s needs and requirements are identified, preliminary studies are performed, a site is selected, and a preliminary budget and schedule are established. (PDPG 3.4.1)
Term
List the 6 Project Delivery Methods.
Definition
 Design-bid-build
 Design-negotiate-build
 Design-build
 Construction management
 Owner-build
 Integrated project delivery
(PDPG 3.4.2)
Term
What are the 2 commonly recognized phases of design?
Definition
Schematic design and Design Development.
Term
What are deliverables?
Definition
Contractually required information delivered by the design team. (PDPG 3.4.3)
Term
Name the two major types of construction docs.
Definition
Procurement and contract documents.
Term
Describe what happens during the Procurement Phase.
Definition
Bidding/Negotiating/Purchasing (Procurement). Stage in the facility life cycle that allows the prospective contractor to examine bidding documents, visit the site, request clarifications and interpretations, propose substitutions, and finally, prepare a bid or price for executing the work. Acceptance of the contractor’s bid or negotiated sum and other conditions will result in award of contract and commencement of work. (PDPG 3.4.5)
Term
What 3 project factors establish the quality of a project?
Definition
Extent, time and cost.
Term
Define Extent.
Definition
The magnitude, form, function, and complexity of the project will have a direct bearing on the project delivery method and the number of participants. Generally, the greater the magnitude of the project, the greater the number of participants, the more the construction process is compounded. (PDPG 7.1.4)
Term
Cost.
Definition
Number of different methods are used for determining and stating amounts of cost or compensation within agreements. When contract is bid or negotiated, the basis of payment that will be used in the contract is clearly stated in bidding documents or request for proposal. When the contract is executed the bid or negotiated basis of payment is included in the contract. (PDPG 7.1.6)
Term
How do the AIA, EJCDC and CSI define design as occurring?
Definition
AIA (3): schematic design, design dev, and constr. docs.
EJCDC (2): prelim design and final design (incl. const. docs)
CSI (2): Schematic and design dev.
Term
Describe what occurs during the Schematic Design Phase.
Definition
Site plan and area relationships may be defined, the general size, shape, and massing of building elements are determined, elevations and exterior finishes established, and conceptual design criteria for structural, mechanical, and electrical systems identified. Written documents usually consist of preliminary project descriptions and preliminary cost projections. (PDPG 8.8.3)
Term
Describe the Design Development phase.
Definition
Design development documents fix and describe the size and character of the entire project, including architectural, structural, mechanical, and electrical systems. Documentation includes more precise and specific drawings, physical or electronic models, and outline specifications. (PDPG 8.8.4)
Term
Prototype Design
Definition
Single design developed for multiple projects on different sites. Establishes a consistent project identity and purpose that is readily identified by facility users. Each project is site adapted to a particular site and requirements of the authorities having jurisdiction. Can enhance the efficiency of design, construction, and facility management stages of the project life cycle. (PDPG 8.8.1.2)
Term
Integrated Project Delivery (IPD).
Definition
A project delivery approach that integrates people, systems, business structures, and practices into a process that collaboratively harnesses the talents and insights of all participants to optimize project results, increase value to the owner, reduce waste, and maximize efficiency through all phases of design, fabrication, and construction.” (PDPG 7.7)
Term
Describe UniFormat.
Definition
A uniform classification system for organizing preliminary construction information into a standard order or sequence on the basis of elements and systems. Derived from OmniClass Table 21: Elements. (PDPG 11.3.7.2)
Term
What was the basis used for OmniClass development?
Definition
Derived from internationally accepted standards developed by International Organization of Standards (ISO). (PDPG 11.3.7.1)
Term
How many divisions are there in MasterFormat?
Definition
50. Derived from OmniClass Table 22: Work Results.
Term
What are the 4 C's of communication?
Definition
Clear, concise, correct, complete.
Supporting users have an ad free experience!