Term
| Project Cost Management Processes: |
|
Definition
Plan Cost Estimate Costs Determine Budgets Control Costs |
|
|
Term
|
Definition
| are revenues minus expenditures |
|
|
Term
|
Definition
| is the ratio of revenues to profits |
|
|
Term
|
Definition
| considers the total cost of ownership, or development plus support costs, for a project |
|
|
Term
|
Definition
| determines the estimated annual costs and benefits for a project and the resulting annual cash flow |
|
|
Term
|
Definition
| benefits are those costs or benefits that an organization can easily measure in dollars |
|
|
Term
| Intangible costs or benefits |
|
Definition
| costs or benefits that are difficult to measure in monetary terms |
|
|
Term
|
Definition
| costs that can be directly related to producing the products and services of the project |
|
|
Term
|
Definition
| costs that are not directly related to the products or services of the project, but are indirectly related to performing the project |
|
|
Term
|
Definition
| is money that has been spent in the past; when deciding what projects to invest in or continue, you should not include sunk costs in a budget |
|
|
Term
|
Definition
| Cost estimates are influenced by many factors including labor rates, materials cost, economic factors, risk factors, etc. Expert judgment provides insights into evaluation of these factors into cost estimation. |
|
|
Term
|
Definition
| Using values such as scope, cost estimates, time estimates, complexity from similar projects. Use actual costs from prior project and adjust for known differences. This is a part of cost estimation. |
|
|
Term
|
Definition
| Uses statistical techniques to predict from historical data. Can produce higher levels of estimates depending on the sophistication of the statistical techniques. |
|
|
Term
|
Definition
| Uses WBS to estimate each component of work. The costs of each work package is the rolled up into subtotals for tasks. |
|
|
Term
|
Definition
| Contingency reserves (contingency allowances). Can be percentage of estimated cost, an actual $ figure or determined through parametric analysis |
|
|
Term
| Rough order of magnitude (ROM) |
|
Definition
| Accuracy ranges from -25% to +75% (just know large range). Usually used in initiation process to establish high-level budget. |
|
|
Term
|
Definition
| Accuracy ranges from -10% to +25% (just know medium range). Usually used in planning process to establish early budget estimates. Also used in top-down estimating (Using prior project to estimate project costs) |
|
|
Term
|
Definition
| Accuracy ranges from -5% to + 10% (just know small range). Usually used late in planning phase and in bottom-up estimating (use of WBS) |
|
|
Term
| Earned Value Management (EVM) |
|
Definition
- Method of performance measurement. It integrates project scope, costs and schedule to help project team assess status, performance and progress. EVM monitors 3 key dimensions: -Planned Value -Earned Value - Actual Cost This is a part of "Control Costs" |
|
|
Term
|
Definition
| formerly called the budgeted cost of work scheduled (BCWS), also called the budget, is that portion of the approved total cost estimate planned to be spent on an activity during a given period |
|
|
Term
|
Definition
| formerly called actual cost of work performed (ACWP), is the total of direct and indirect costs incurred in accomplishing work on an activity during a given period |
|
|
Term
|
Definition
| formerly called the budgeted cost of work performed (BCWP), is an estimate of the value of the physical work actually completed |
|
|
Term
|
Definition
All start wit hEV -V =EV-AC - SV=EV -PV - CPI=EV / AC - SPI=EV/PV Variance means subtract Index means divide Less than 1 is bad in an index Negative is bad in a variance |
|
|
Term
|
Definition
Cost variance is the difference between the earned value and the actual cost. CV = EV -AC |
|
|
Term
|
Definition
Schedule variance is the difference between the earned value and the planned value. SV = EV -PV |
|
|
Term
| Cost Performance Index (CPI) |
|
Definition
Cost performance index is the amount of work the project is completing per dollar spent on the project. CPI= EV /AC |
|
|
Term
| Schedule Performance Index (SPI) |
|
Definition
Cost performance index reveals how close the project is to being on schedule. SPI= EV /PV |
|
|
Term
| Estimate to Complete(ETC) |
|
Definition
| Estimate to completion is a “best guess” as to how much money it will take to complete the project. |
|
|
Term
| Estimate at Completion(EAC) |
|
Definition
| Estimate at completion is a “best guess” as to what the total cost of the project will be based on the experiences with the project so far. |
|
|
Term
| Control Cost Cause of Variation |
|
Definition
- Things beyond our control (force majeure) - Bad planning - Poorly designed contracts - Unrealistic cost estimates - Unrealistic time estimates - Changes in technology - Changes in regulations - Laissez-faire project management - Poor risk management |
|
|
Term
| To Complete Performance Index |
|
Definition
| is a forecast of cost performance that must be attained on remaining work in order to meet a specified management goal or goals. This is a part of cost control |
|
|