Term
| Nominal Group Technique (NGT) |
|
Definition
| Brainstorming plus voting process = ranked ideas (small groups) |
|
|
Term
|
Definition
| Gather requirements from experts whose anonmity is maintained. |
|
|
Term
|
Definition
| Working model of expected product. |
|
|
Term
|
Definition
| limiting factors (budgets, deadlines, contractactual constraints...etc) |
|
|
Term
| Inputs WBS, WBS Dictionary, Scope Baseline |
|
Definition
- Project Scope Statements - Requirements docs |
|
|
Term
|
Definition
|
|
Term
|
Definition
|
|
Term
|
Definition
| Grouping of project components |
|
|
Term
|
Definition
| Detail description of each work package |
|
|
Term
|
Definition
| WBS + WBS dictionary + Scope statement |
|
|
Term
|
Definition
|
|
Term
| Finish to Start (most common) |
|
Definition
| A must finish before B can start |
|
|
Term
|
Definition
| A must start before B can start |
|
|
Term
|
Definition
| A must finish before B can finish |
|
|
Term
|
Definition
| A must start before B can finish |
|
|
Term
| Precedence Diagraming Method |
|
Definition
- AKA Activity on Mode (AOM) - Used in Critical Path Method - Uses boxes or rectangles as nodes to represent activities. - Connect boses with arrows which represent dependencies - Includes all 4 relationships (FF, FS, SS & SF) |
|
|