Term
|
Definition
| A sequence of discrete work packages and planning packages (or lower-level tasks/activities) in the network that has the longest total duration through an end point that is calculated by the schedule software application. Discrete work packages and planning packages (or lower-level tasks/activities) along the CP have the least amount of float/slack (scheduling flexibility) and cannot be delayed without delaying the finish time of the end point effort. |
|
|
Term
|
Definition
| take funds from lower priority program (Bill Payer) within the total budget authority |
|
|
Term
|
Definition
reprogramming (BTR) actions are approved by the individual Services and Defense Agencies. Do not meet the criteria for prior approval or internal reprogramming. |
|
|
Term
| Reprogramming actions Congressional Prior Approval |
|
Definition
requests are submitted through USD (C) to Congress on DD Form 1415-1 |
|
|
Term
| Reprogramming actions Congressional Prior Approval |
|
Definition
| Results in a procurement quantity increase of a major end item (unless specific congressional language allows additional quantities). |
|
|
Term
| Reprogramming actions Congressional Prior Approval |
|
Definition
| Affects a congressional special interest item. An exception is given if the funds will be used for the same purpose for which appropriated; then an Internal Reprogramming (IR) action would be used |
|
|
Term
| Reprogramming actions Congressional Prior Approval |
|
Definition
| Involves the use of the Secretary of Defense’s general transfer authority (i.e., movement of any amount of funds between appropriations). |
|
|
Term
| Reprogramming actions Congressional Prior Approval |
|
Definition
| An exception is given if the funds will be us for the same purpose for which appropriated; then an IR action would be used. |
|
|
Term
| Reprogramming actions Congressional Prior Approval |
|
Definition
| Establishes New Programs (i.e., New Starts), defined as any program not explicitly justified to and funded by the Congress. |
|
|
Term
| Reprogramming actions Congressional Prior Approval |
|
Definition
| Exceeds the dollar threshold for reprogramming between elements |
|
|
Term
|
Definition
| is done through the use of DD Form 1415-3 and requires approval by the USD (C). Realigns appropriated funds to a different line item or appropriation for proper execution of the same requirement with no change in purpose. |
|
|
Term
| Congressional Notification Letter (Internal reprogramming) |
|
Definition
| (in advance of initiation) requires a 30-day notification to the Defense Committees. |
|
|
Term
| Following are appropriate for prior notification actions: |
|
Definition
New programs or line items not otherwise requiring prior approval by Congress. New procurement programs, including modifications, costing less than $20 million for the entire effort. New development programs costing less than $10 million for the entire effort. Initiation of safety programs or safety modifications costing less than $20 million for the entire effort. Termination of programs falling within the “below threshold reprogramming” amounts |
|
|
Term
|
Definition
| is defined as the probability that an item is in an operable state at the start of a mission when the mission is called for at a random point in time. The user is most concerned about this parameter since it reflects the basic readiness of the system, and Ao may often be specified in the Capability Development Document (CDD)/Capability Production Document (CPD). |
|
|
Term
| Mean Logistics Delay Time (MLDT) |
|
Definition
| is an indicator of the average time a system is awaiting maintenance and generally includes time for 1) Locating parts and tools, 2) Locating, setting up or calibrating test equipment, 3) Dispatching personnel 4) Reviewing technical manuals, 5) Complying with supply procedures, and 6) Awaiting transportation. The MLDT is largely dependent upon the logistics support structure and environment. |
|
|
Term
| Best Practices and Use of COTS Software in Software Systems Development |
|
Definition
• Viewing the software "content," particularly complex algorithms and functional flows, as enabling technologies requiring maturation and risk reduction prior to MS B; • Developing architectural-based software systems that support open system concepts; • Exploiting commercial, off-the-shelf (COTS) computer systems products; |
|
|
Term
| Best Practices and Use of COTS Software in Software Systems Development |
|
Definition
• Allowing incremental improvements based on modular, reusable, extensible software; • Identifying and exploiting, where practicable, Government and commercial software reuse opportunities before developing new software; • Selecting the programming language in context of the systems and software engineering factors that influence system performance, overall Life-cycle costs, risks, and the potential for interoperability; |
|
|
Term
| Best Practices and Use of COTS Software in Software Systems Development |
|
Definition
• Using DoD standard data and following data administrative policies in DoD Directive 8320.1; • Selecting contractors with domain experience in developing comparable software systems; with successful past performance; and with a mature software development capability and process; • Assessing information operations risks using techniques such as independent expert reviews; |
|
|
Term
| Best Practices and Use of COTS Software in Software Systems Development |
|
Definition
• Preparing for lifecycle software support or maintenance by developing or acquiring the necessary documentation, host systems, test beds, and computer-aided software engineering tools consistent with planned support concepts; • Preparing for lifecycle software support or maintenance by planning for transition of fielded software to the support/maintenance activity; and • Tracking COTS software purchases and maintenance licenses. |
|
|
Term
|
Definition
| The program manager should develop an appropriate test and evaluation strategy for commercial items to include evaluating potential commercial items in a system test bed, when practical; focusing test beds on high-risk items; and testing commercial-item upgrades for unanticipated side effects in areas such as security, safety, reliability, and performance. |
|
|
Term
| Planning, Programming, Budgeting and Execution (PPBE) |
|
Definition
| Within DoD, these requests for future year funds are developed and evaluated in the |
|
|
Term
| The sequence of that budget execution process |
|
Definition
| 1) administrative division (e.g., apportionment and allocation) of those appropriated funds; (2) steps in using (i.e., executing) and reporting the use of appropriated funds; (3) reprogramming appropriated funds to satisfy changes in requirements; (4) laws pertaining to proper use of appropriated funds; (5) statutory life of appropriated funds; and (6) the liquidation (i.e., payment) of those obligations made when contracts were awarded |
|
|
Term
|
Definition
| The primary purposes of the apportionment process are to (1) achieve the most effective and economical use of amounts made available, and (2) prevent agencies from obligating funds in a manner that would result in a deficiency or require a supplemental appropriation. |
|
|
Term
|
Definition
| situations in which a President may desire to not apportion the budget authority contained in an appropriations act – even though he signed that act into law. The Budget and Impoundment Control Act of 1974 permits the President some latitude in the release of that appropriated funding. Under the provisions of that law, the President may identify a specific amount of funding contained in an appropriations act for a specific purpose and initiate an impoundment action. There are two types of impoundment actions specified in the Budget and Impoundment Control Act of 1974: deferral and rescission. |
|
|
Term
|
Definition
| a temporary impoundment or withholding of funds (e.g., due to technical problems or schedule slip). |
|
|
Term
|
Definition
| is a permanent impounding or cancellation of funds (e.g., due to program cancellation). |
|
|
Term
|
Definition
| Subsequent to the OMB apportionment action, USD (C) allocates DoD’s budget authority to the various military services and defense agencies based on appropriations made by Congress. |
|
|
Term
|
Definition
| Non-Economy Act orders citing an annual or multiyear appropriation must serve a bona fide need arising, or existing, in the fiscal year (or years) for which the appropriation is available for new obligations. |
|
|
Term
|
Definition
| Provisions of US Code, Title 31, Section 1501 govern recording of an obligation. An amount shall be recorded as an obligation only when supported by documentary evidence of an order required by law to be placed with an agency or when other specific criteria are met. |
|
|
Term
| Types of Reprogramming Actions |
|
Definition
| There are four types of reprogramming actions available to DoD: (1) Congressional Prior Approval; (2) Internal; (3) Congressional Notification; and (4) Below-Threshold Reprogramming (BTR). The following policy statements pertaining to each type of reprogramming action are a combination of what is contained in the cited chapters of the FMR and the 10 Feb 2006 USD (C) memorandum on BTR actions. |
|
|
Term
|
Definition
| US Code, Title 31, Section 1301, which deals with the application of monies appropriated by Congress, requires funds be used only for programs and purposes for which the appropriation is made. Generic examples of a violation of the Misappropriation Act include the use of one of the procurement appropriations for an effort that should properly be funded with an RDT&E appropriation or the use of an Operations and Maintenance (O&M) appropriation to buy an item for which one of the procurement appropriations should have been used |
|
|
Term
|
Definition
|
|
Term
|
Definition
|
|
Term
|
Definition
|
|
Term
| Procurement (excluding SCN) |
|
Definition
|
|
Term
| Procurement SCN (Shipbuilding & Conversion, Navy) |
|
Definition
|
|
Term
|
Definition
|
|
Term
|
Definition
| During the five year expired status period, which is the same for all Defense appropriations, only limited uses can be made of those expired appropriations. According to US Code, Title 31, Section 1553, during this “expired” status period, the appropriation account “retains its fiscal year identity and remains available for recording, adjusting, and liquidating obligations properly chargeable to that account”. |
|
|
Term
|
Definition
| after the five year expired status period, any remaining balance in an appropriation account (whether obligated or unobligated) “shall be cancelled and thereafter shall not be available for obligation or expenditure for any purpose”. |
|
|
Term
|
Definition
Based on Detailed information Updated periodically “Bottoms-up” from Control Account Level |
|
|
Term
Government Program Office EAC |
|
Definition
Review Contractor EAC/LRE Formulas – Sanity Check Identify Risk Develop PMO EAC Range Not “plug and chug” – more than just EV status Add PM Perspective Analysis and incorporation of all program data |
|
|
Term
|
Definition
Lack of Program Details Usually Formula-Based at top level Sometimes Related to Database (history of past programs) |
|
|
Term
| Budgeted Cost of Work Scheduled (BCWS) |
|
Definition
| = Planned Value - represents the value of work planned to be accomplished. When BCWS is portrayed over the contract period, it equates to the Performance Measurement Baseline (PMB), the time-phased budget plan against which contract performance will be measured. |
|
|
Term
| Budgeted Cost of Work Performed (BCWP) |
|
Definition
| Earned Value – represents the value of the work accomplished in relation to the PMB |
|
|
Term
| Actual Cost of Work Performed (ACWP) |
|
Definition
| Actual cost of work accomplished |
|
|
Term
|
Definition
|
|
Term
|
Definition
|
|
Term
|
Definition
|
|
Term
| Schedule Performance Index |
|
Definition
|
|
Term
| Estimate at Completion (General) |
|
Definition
| Actuals to Date + (Remaining Work/Efficiency Factor) |
|
|
Term
| Efficiency (Performance) Factors = Various |
|
Definition
CPICUM Composite (CPICUM x SPICUM) 3-Period (month)CPI 6-Period (month)CPI Weighted (.8CPICUM + .2SPICUM) |
|
|
Term
|
Definition
| Cumulative CPI: tends to be the most optimistic estimate |
|
|
Term
|
Definition
| Composite (CPICUM x SPICUM): tends to be the most pessimistic estimate; weights cost and schedule equally |
|
|
Term
|
Definition
| Three period (month) CPI: shows most current cost performance |
|
|
Term
|
Definition
| Six period (month) CPI: shows longer timeframe for cost performance – may be more accurate (or less accurate) regarding true trends |
|
|
Term
|
Definition
| MR is budget set aside for unplanned events that may arise during the course of a project. Because MR is budget that is not yet tied to work, it does not form part of the performance measurement baseline. The MR budget should be commensurate with the level of risks identified by the contract and/or withheld for management control purposes. |
|
|
Term
|
Definition
| MR is part of the contract’s Negotiated Contract Cost (NCC), but MR is not included as part of the contract’s performance measurement baseline (PMB). MR will be applied to the PMB if and when previously unanticipated, in-scope work is realized. |
|
|
Term
|
Definition
| MR is not used to offset accumulated overruns or under runs and it is not a contingency budget than can be used for new work or eliminated from the contract price during subsequent negotiations. The budget being held in reserve must not be viewed by the government as a source of funding for added work scope. |
|
|
Term
|
Definition
Functional testing of a software unit without knowledge of how the internal structure or logic will process the input to obtain the specified output |
|
|
Term
|
Definition
Structural testing of the internal logic and software structure provides an opportunity for more extensive identification and testing of critical paths. |
|
|
Term
|
Definition
Development Test and Evaluation (DT&E) and Operational Test and Evaluation (OA (Operational Assessment), IOT&E) events must be designed to provide for data collection processes and instrumentation that will measure system responses and allow data analysts to identify the appropriate causes of malfunctions. |
|
|
Term
|
Definition
are risk-reducing techniques that are applied to major software development efforts. The primary purpose of IV&V is to ensure that software meets requirements and is reliable and maintainable. |
|
|
Term
|
Definition
Integration of the software released from the SIL for full-up testing with actual system hardware in a Hardwarein- the-Loop (HWIL) facility marks a significant advance in the development process. |
|
|
Term
|
Definition
When you enter into a UCA using a NTE price you increase Section A (Face Value) and Section B (CLINs) by that NTE amount. However you only obligate 50% of the available funds on the contract in Section G. Once the price is definitized/negotiated then the contract modification that definitzes it would reflect a negative amount for Section A (Face Value), a negative value for the CLIN(s) Section B, and an increase in Section G (Funding) to the amount obligated (assuming it is above the 50% amount originally obligated). Of course you must have 100% of the NTE on the document that "commits" the funds (ACD, PR&C, AF Form 9 etc.). |
|
|
Term
|
Definition
| both provide the Government the right to change a contract (design, drawings, specifications, description of services, place of performance, method of shipment or packing, time of performance). These clauses even give the Contracting Officer the unilateral right to direct the contractor to accomplish the change, but protect the contractor with the right to submit a request for equitable adjustment. |
|
|
Term
|
Definition
(Noncommercial Contracts) at FAR 52.243-1 allows unilateral changes in the following:
(a) The Contracting Officer may at any time, by written order, and without notice to the sureties, if any, make changes within the general scope of this contract in any one or more of the following:
(1) Drawings, designs, or specifications when the supplies to be furnished are to be specially manufactured for the Government in accordance with the drawings, designs, or specifications.
(2) Method of shipment or packing.
(3) Place of delivery.
It does not allow you to extend the term of the contract |
|
|
Term
|
Definition
| An act of Congress which permits a federal program or activity to begin or continue from year to year. It sets limits on funds that can be appropriated, but does not grant funding which must be provided by a separate congressional appropriation. |
|
|
Term
|
Definition
| Legislation that establishes or continues the legal operation of a program or agency for a period of time; sanctions a particular type of obligation or expenditure; limits the amount of budget authority provided; or authorize the appropriation of funds as necessary |
|
|
Term
|
Definition
| An authorization by an act of Congress that permits Federal agencies to incur obligations and make payments from the Treasury. An appropriation usually follows enactment of authorizing legislation. An appropriation act is the most common means of providing Budget Authority (BA). Appropriations do not represent cash actually set aside in the Treasury; they represent limitations of amounts which agencies may obligate during a specified time period |
|
|
Term
| Procurement appropriations |
|
Definition
| fund those acquisition programs that have been approved for production (to include Low Rate Initial Production (LRIP) of acquisition objective quantities), and all costs integral and necessary to deliver a useful end item intended for operational use or inventory upon delivery. |
|
|
Term
| Operation and Maintenance (O&M) |
|
Definition
| appropriations fund expenses such as civilian salaries, travel, minor construction projects, operating military forces, training and education, depot maintenance, stock funds, and base operations support. Military Personnel (MILPERS) appropriations fund costs of salaries and other compensation for active and retired military personnel and reserve forces based on end strength |
|
|
Term
| Research, Development, Test and Evaluation (RDT&E) |
|
Definition
| appropriations fund the efforts performed by contractors and government activities required for the Research and Development (R&D) of equipment, material, computer application software, and its Test and Evaluation (T&E) to include Initial Operational Test and Evaluation (IOT&E) and Live Fire Test and Evaluation (LFT&E). RDT&E also funds the operation of dedicated R&D installations activities for the conduct of R&D programs. |
|
|
Term
| Military Construction (MILCON) |
|
Definition
| appropriations fund major projects such as bases, schools, missile storage facilities, maintenance facilities, medical/dental clinics, libraries, and military family housing. |
|
|
Term
| Congressional Enactment Process (CEP) |
|
Definition
Action by the Congress on the President's Budget (PB). Includes hearings, budget resolution, authorizations and appropriations acts. Result is appropriations (funding) for Federal Government. Second of four phases in the DoD Resource Allocation Process (RAP). |
|
|
Term
| Congressional (Budget) Enactment |
|
Definition
| is a three-step process: (1) budget resolution, (2) authorization and (3) appropriation. The defense budget is a highly visible, politically sensitive portion of the President's Budget (PB), and its enactment is subject to frequent and significant delays as members of Congress attempt to use passage of the annual appropriations acts as a political tool. |
|
|
Term
|
Definition
| Bilateral written modification to a contract by which the government and the contractor settle price and/or performance adjustments to the basic contract. Best option |
|
|
Term
|
Definition
| A contract change without formal written authority. |
|
|
Term
|
Definition
| you are funded against the target price (cost + proffit) |
|
|
Term
| Budget Estimate Submission (BES) |
|
Definition
| The DoD component’s budget submissions to the Office of the Secretary of Defense (OSD) showing budget requirements for inclusion in the DoD budget during the Planning, Programming, Budgeting, and Execution (PPBE) process. |
|
|
Term
|
Definition
| O&M, MILPER appropriations |
|
|
Term
| Incremental Funding – RDT&E -Exceptions |
|
Definition
| 9, 15, and 18 month exception |
|
|
Term
Procurement, MILCON - Exceptions to Full Funding |
|
Definition
Multiyear Procurement Advance Procurement |
|
|
Term
| Procurement, MILCON Funding |
|
Definition
|
|
Term
| Annual Funding Policy - Applies to O&M and MILPER Appropriation Categories |
|
Definition
| Prepare annual budget request on basis of funding needed to operate and maintain DoD activities and pay personnel for a 12 month budget period |
|
|
Term
| Annual Funding Policy - Applies to O&M and MILPER Appropriation Categories |
|
Definition
| Intent of policy: To provide only those funds required to pay expenses associated with “normal” operations of DoD activities for a 12 month period |
|
|
Term
| Annual Funding Policy - Service Contract Exception |
|
Definition
Exception to budgeting for “Fiscal Year” period U.S. Code, Title 10, provides DoD authority to budget for and obligate funds for severable service contracts for periods crossing fiscal years provided the contract period does not exceed 12 months
Funds made available for a given fiscal year may be obligated for the total amount of that contract |
|
|
Term
| Incremental Funding Policy - Applies to RDT&E Appropriation Category |
|
Definition
| Prepare annual budget request on basis of incremental funding required to cover only those costs expected to be incurred for work to be done during a given fiscal year |
|
|
Term
| Incremental Funding Policy - Applies to RDT&E Appropriation Category |
|
Definition
| Intent of policy: To achieve effective “rationing” of scarce funds among research programs |
|
|
Term
|
Definition
DODI 5000.02 Requirement Full funding (i.e., the inclusion of the dollars and manpower needed for all current and future efforts to carry out the acquisition strategy in the budget and out-year program), which shall be programmed in anticipation of each Milestone (A, B, C and FRPDR decisions |
|
|
Term
|
Definition
DOD Financial Management Regulation Requirement For budgeting purposes, funding for each fiscal year shall be sufficient to procure complete, usable end items |
|
|
Term
|
Definition
This policy applies to: programming and budgeting actions required quantities on a “year-to-year” basis quantities that can be delivered during a future 12 month period (as a maximum period) each separate fiscal year as an independent action |
|
|
Term
|
Definition
This policy does not require the total procurement quantity desired over the entire life of the program to be budgeted in any one single fiscal year. |
|
|
Term
| Advance Procurement Exception |
|
Definition
Lead-time of the item is greater than life of the appropriation, or Why an exception? Procurement action is not for a usable end item. |
|
|
Term
| Multiyear Procurement (MYP) Exception |
|
Definition
Associated with Economic Order Quantity (EOC) of components, parts or materials of the end item Why an exception? Contracted deliveries will exceed the 12 month funded delivery period. Congress normally appropriates on a year-to-year basis without committing to a program’s acquisition quantity. |
|
|
Term
| Exception to Full Funding Policy |
|
Definition
| A single contract for a specific quantity of usable end items to be delivered over a period of time greater than one year but not more than five years |
|
|
Term
| Multiyear Procurement - Benifits |
|
Definition
Brings stability to the acquisition and budgeting process Provides assurance to contractor of future years business, encourages contractor investment in manufacturing process, and increases contractor productivity = lower cost to government |
|
|
Term
| Multiyear Procurement - Potential Problems |
|
Definition
Government liable for a penalty (in a decreasing amount) for early cancellation of contract Can not budget for that cancellation/termination liability Controversial concept (both in Congress & OSD) |
|
|
Term
| Cancellation Costs may cover: |
|
Definition
Non-recurring Costs Recurring Cost (with approval of Agency Head and USD (C)) |
|
|
Term
|
Definition
Negotiated along with other provisions of the contract A decreasing amount each year Not an additional amount to be budgeted |
|
|
Term
| Two types of Product Improvements - Changes to a Fielded System |
|
Definition
One that increases performance (i.e., “enhances the performance envelope”) One that does not increase performance |
|
|
Term
|
Definition
The “realignment of budget authority from a purpose fro which appropriated to finance another (usually emergent) requirement.” |
|
|
Term
|
Definition
Only funds “currently available” for obligation can be “reprogrammed.” Funds identified in the FYDP can be “shifted” or “moved.” |
|
|
Term
|
Definition
A “Transfer” occurs when a reprogramming action results in movement of budget authority From one appropriation to another (i.e., O&M Army to O&M Navy, Aircraft Procurement USAF To RDT&E USAF) |
|
|
Term
|
Definition
Requires approval of USD (C) No change in purpose Documents realignment of funds to a different line item May be used to correct mistakes in appropriations Does “not” mean “internal to a program” |
|
|
Term
| Reprogramming - Congressional Prior Approval |
|
Definition
Procurement quantity increase Affects item of “special Congressional interest” Exceeds specific $$ thresholds Establishes a new program – or Involves the termination of an approved program Usually done by Services as part of an annual omnibus reprogramming submission |
|
|
Term
| Reprogramming - Congressional Notification |
|
Definition
Congressional Notification Requires 30-day notification to Defense Committee No action until 30 days after such notification Establishes a new program Est. new “procurement” program, including mods costing <$20M for the entire effort Est. new development effort costing <$10M for the entire effort Initiation of safety modifications of <$20M Termination of programs falling below BTR amounts |
|
|
Term
|
Definition
| Phase 1 current account(1 to 5 years), Phase 2 Expired Account(5 years), Phase 3 Closed Canceled account |
|
|
Term
| government to mandate metrics |
|
Definition
In most cases, it is inappropriate for the government to mandate metrics or manufacturing techniques to the contractor; that does not mean the government shouldn't incent defense contractors to adopt proven best manufacturing practices. |
|
|
Term
| The lean manufacturing process model |
|
Definition
uses flat organizational structures to encourage initiative and the flow of information to highlight and address defects, equipment abnormalities, operator errors and organizational deficiencies. A lean manufacturing environment strives to eliminate waste and achieve incremental, yet continuous, improvement. |
|
|
Term
|
Definition
offer the potential to save significant operations and support costs through dramatic gains in equipment reliability. |
|
|
Term
| A key aspect of a reliability |
|
Definition
improvement is controlling variability in the production and assembly process. |
|
|
Term
| Post Deployment Review (PDR) |
|
Definition
afford PMs the opportunity for formal feedback on recently fielded systems. The PM uses PDRs of the system, beginning at IOC, to verify whether the fielded system continues to meet or exceed thresholds and objectives for cost, performance, and support parameters approved at the full rate production review. |
|
|
Term
| Post Deployment Review (PDR) |
|
Definition
PDRs nominally occur every 3-5 years after IOC or when precipitated by changes in requirements/design or performance problems |
|
|
Term
| The Defense Priorities and Allocations System (DPAS) |
|
Definition
Program provides for Special Priorities Assistance (SPA) to address critical production-related problems. Although SPA can be an extremely useful tool for a rated program, it should not be considered a panacea. |
|
|
Term
|
Definition
is a major decision point – and reliability requirements are "requirements." Decisions to "press on" in spite of less than stellar test results for system reliability will eventually bring the program to a halt. |
|
|
Term
| Recovering from a major test failure |
|
Definition
has potentially significant cost, scheduling, contracting, acquisition strategy, test and evaluation, and software development issues. |
|
|
Term
| Use of the "changes clause" |
|
Definition
can allow rapid response to a programmatic requirement but the specific rules for its use must be clearly understood. |
|
|
Term
| The ability to make a rapid Rough Order Magnitude (ROM) |
|
Definition
estimate is necessary at times to expedite a high priority contract action. |
|
|
Term
| System reliability and maintainability |
|
Definition
are central to controlling operations and maintenance costs. PMO personnel need to understand the meanings of the various definitions of availability (inherent, achieved, and operational) and what the contractor's design can (and cannot) affect. |
|
|
Term
| Legacy reuse and commercial software |
|
Definition
offer the potential for major savings in cost and schedule if used appropriately. PMO personnel must understand the risk inherent in utilizing either of these software options. |
|
|
Term
|
Definition
can be used to reduce programmatic risk by providing capabilities in increments when the necessary technology is mature. The user (and MDA) must agree to any proposed revision to the approved acquisition strategy/program structure regarding the delivery of user requirements. |
|
|