| Term 
 
        | Function of Liquid Rad Waste System |  | Definition 
 
        | Collect, process, reclaim, or dispose of radioactive waste such that the discharge of the radioactive waste to the environment will be limited. |  | 
        |  | 
        
        | Term 
 
        | Drywell drains associated with identified leakage |  | Definition 
 | 
        |  | 
        
        | Term 
 
        | Drywell drains associated with unidentified leakage |  | Definition 
 | 
        |  | 
        
        | Term 
 
        | Discuss RHR Pump Room floor drains |  | Definition 
 
        | Provided with orifices to limit the amount of back flooding into these rooms in the event the torus area gets flooded or one of the RHR Pump Rooms becomes flooded. |  | 
        |  | 
        
        | Term 
 
        | Drywell Floor Drain Sump Monitoring system operability |  | Definition 
 
        | Either the flow or level monitoring portion of the system must be operable. The system consists of a sump discharge flow integrator, one sump level recorder, and one sump fill rate computer point (rate of change). The drywell floor drain sump monitoring system is operable whenever one of these channels is operable. |  | 
        |  | 
        
        | Term 
 
        | "Action, per B.07.01-05, to be taken if TB Equip drain sump becomes contaminated." |  | Definition 
 
        | "Place HS-2562, COND DRIP TANK TO HOTWELL, in the COLL (collector) position. This action sends TB equip drain sump to rad waste." |  | 
        |  | 
        
        | Term 
 
        | Precaution associated with sending DW Equip drain sump to the waste collector tank. |  | Definition 
 
        | "Due to elevation head, water hammer during pump discharge check valve slam has ruptured the rupture disk inside the drywell." |  | 
        |  | 
        
        | Term 
 
        | Precaution associated with DW Floor drain sump pumps |  | Definition 
 
        | "When placed in run, will not auto stop upon reaching low level trip setting and thus requires continuous monitoring." |  | 
        |  | 
        
        | Term 
 
        | Expected auto start and trip of DW Floor drain sump |  | Definition 
 
        | Auto start: 8.6-9.0 inches; Auto trip: 2.2-2.6 inches |  | 
        |  | 
        
        | Term 
 
        | DW Equip drain sump pump power supplies |  | Definition 
 | 
        |  | 
        
        | Term 
 
        | RX Build equip drain sump pump power supply |  | Definition 
 | 
        |  | 
        
        | Term 
 
        | Cond drip tank pump power supplies |  | Definition 
 | 
        |  | 
        
        | Term 
 
        | DW Floor drain sump pump power supplies |  | Definition 
 | 
        |  | 
        
        | Term 
 
        | RX Build floor drain sump pump power supplies |  | Definition 
 | 
        |  | 
        
        | Term 
 
        | TB Floor Drain and TB Norm Waste sump pump power supplies |  | Definition 
 
        | Both have MCC-131 and MCC-121 |  | 
        |  | 
        
        | Term 
 
        | Liquid Radwaste Normal flow line-up |  | Definition 
 
        | Recycle: Pump from waste collector tank and floor drain collector tank, through waste collector filter, back to tanks. |  | 
        |  | 
        
        | Term 
 
        | Liquid Radwaste make-up to CSTs flow path |  | Definition 
 
        | From waste collector tank and floor drain collector tank, through waste collector filter, through waste demineralizer to waste sample tanks (2) or floor drain sample tank where the water is sampled. Once the determination that the water is clean is made, it is sent to CSTs. |  | 
        |  | 
        
        | Term 
 
        | Which Scram Discharge Volume does RB Equip Drain Tank receive? |  | Definition 
 
        | East Scram Discharge Volume (Equip = East) |  | 
        |  | 
        
        | Term 
 
        | Which Scram Discharge Volume does RB Floor Drain Tank receive? |  | Definition 
 
        | West Scram Discharge Volume |  | 
        |  | 
        
        | Term 
 
        | DW Equip and Floor drain system response to Group II primary containment isolation |  | Definition 
 
        | Isolation valves close which trips the pump REGARDLESS of mode. |  | 
        |  | 
        
        | Term 
 
        | What determines whether condensate drip tank is sent back to main condenser or waste collector tank? |  | Definition 
 
        | "Sent to main condenser if condensate drip tank discharge pressure greater than 10 psig (indicates pump running) and conductivity less than 1 micro-mho. Otherwise, sent to waste collector tank." |  | 
        |  | 
        
        | Term 
 
        | Which drywell drain sump has a heat exchanger? |  | Definition 
 
        | Drywell equipment drain sump |  | 
        |  | 
        
        | Term 
 
        | What happens if drywell equip drain sump reaches 140 degrees F? |  | Definition 
 
        | AO-2560A closes and AO-2560B opens to send water through heat exchanger and back to sump. Resets when temperature goes below 140 degrees F. |  | 
        |  |