What is included in project record documents delivered to the Facility manager for O&M?
Definition
1. O&M data
2. materials and finished data
3. Record submittals and shop drawings
4. Record drawings
5. Record specifications
PDPG 14.1.2
Term
What is a punch list and when is it prepared?
Definition
The punch list identifies defective work and items requiring correction. (PDPG 14.1.2.3) it is prepared prior to substantial completion.
Term
List some examples of documents that need to be submitted to AHJs to meet requirements for use and occupancy.
Definition
Bonds, Easements, Emergency plans, Certificate of occupancy and inspection, signed-off permits, permit review documents
PDPG 14.1.2.4
Term
Who established the date of Substantial completion?
Definition
the A/E. It is documented by the issuance of a certificate of substantial completion.
Term
What is Substantial Completion?
Definition
The point at which the project is sufficiently complete for the owner to occupy or utilize the facility for its intended use.
Term
What does the Owner typically assume responsibility for at Substantial Completion?
Definition
 Routine maintenance
 Utilities
 Security
 Property insurance
 Liability (PDPG 14.1.2.5)
Term
What are the two types of commissioning?
Definition
Total building commissioning and Systems and Equipment commissioning.
Term
What is the usual limit for a contractor correction period?
Definition
1 year. Starts at substantial completion. does not limit warranties and other rights to against defective work.
Term
What are the 7 types of maintenance?
Definition
 Maintenance
 Emergency maintenance
 General maintenance
 Preventive maintenance
 Routine maintenance
 Renovation/modification
 Deferred maintenance
(PDPG 14.2.4.2)
Term
What areas of environmental concern might the facility manager be responsible for?
Definition
 Recycling
 Hazardous wastes
 Indoor air quality
 Energy conservation
(PDPG 14.2.4.4)
Term
Local agencies may assess fees for what regulatory process that may affect facility management?
Definition
 Compliance monitoring
 Construction permits
 Life safety system inspections
 Equipment inspections
(PDPG 14.2.4.5)
Term
What are the 4 categories best used to store and archive O&M Materials?
Definition
 Permanent record set
 Regular use set(s)
 Equipment and systems information
 Cleaning and regular maintenance information (PDPG 14.2.5)
Term
What is included in Record Project Manuals?
Definition
 Changes made to the project manual by addenda, change orders, supplemental
instructions, and field orders
 Identification of materials and systems incorporated in construction, rather than all
manufacturers, materials, and systems identified in the contract documents (PDPG 14.2.5.1)
Term
What are record Submittals and why are they important?
Definition
Record submittals can include a complete set of the information on materials, equipment, and systems incorporated into the project including the following: a complete set of shop drawings, product data, test reports, and other information on materials, equipment, and systems incorporated into the project. (PDPG 14.2.5.1)
Term
What issues do facility evaluations address?
Definition
facility use, effectiveness, efficiency, operational cost, maintenance, and environment. Facility evaluations assemble information that will assist in planning and scheduling the following:
 Routine and preventive maintenance
 Capital improvements
 Facility upgrades
 System and equipment replacement
(PDPG 14.2.6)
Term
When should equipment system review and training take place?
Definition
BEFORE substantial completion.
Term
Who generates the punch list?
Definition
The Contractor
Term
Facility managers should perform a post-occupancy evaluation how long after initial occupancy?
Definition
3-6 months