Term
| A201 is also know as the ? |
|
Definition
|
|
Term
| A201 the general conditions set agreement between? |
|
Definition
| They set forth the rights, responsibilities, and relationships of the owner, contractor, and architect. |
|
|
Term
| Contract documents refer to |
|
Definition
| drawing, specs, addenda prior to contract and construction chane directive and change orders |
|
|
Term
| Does A201 GC supersede any prior negotionations and agreements? |
|
Definition
|
|
Term
| any creative work performed by the architect ie sketches drawings, specs are know as... |
|
Definition
|
|
Term
| any creative work performed by the architect ie sketches drawings, specs are know as... |
|
Definition
|
|
Term
| Who is the initial decision maker? |
|
Definition
|
|
Term
| Who owens Instruments of sevice? |
|
Definition
|
|
Term
Article 2 the owner
the owner shall authorize in writing a representitve
to? |
|
Definition
| Authority to act as the owner |
|
|
Term
| Owner shall furnish to the contractor within ____ days after written request all information necesary to file 20 day preliminary notice |
|
Definition
|
|
Term
| True or false. The owner does not need to show contractor proof of financial arrangements prior to commencement of work? |
|
Definition
| False. Owner does if requested and again later if change in contract sum |
|
|
Term
| What does the contractor pay for? |
|
Definition
| permits, licenses, test, and inspections for gov't agency approval as required by contract documents |
|
|
Term
|
Definition
all necessary approval, easements, assessments and charges required for construction, occupancy and use as well as any test and inpections the become neede after the agreement has been executed. Special inspections shall be arragend by the owner |
|
|
Term
| Ownere shall furnish to the contractor? |
|
Definition
| Surveys, lot info, legal limits, utility location and contractor shall be able to rely on this information |
|
|
Term
| According to the A201 Gen. Conditions. Owner has right to stop work if |
|
Definition
| contractro fails to correct work and or repeatedly fails to carry our work in accordanc to the contract documents |
|
|
Term
| According to the A201 Gen. Conditions the Owner has a right to carry out the work if ? |
|
Definition
Contractor fails to carry out work in accord with CD
Owner issue 10 day notice to correct work
10 Days expire and work is not corrected
change order is issued and cost/services plus design fees required to correct work are deducted from contractors fee |
|
|
Term
Article 3-Contractor
A201 GENERAL CONDITIONS
By execution of the contract it means the contractor? |
|
Definition
| Has visited the site become familiar with local conditions correlated observations with the CD requirements |
|
|
Term
| Is the contractor responsible for code compliance? |
|
Definition
|
|
Term
| Is the contractor required to study the CD's prior to starting work? |
|
Definition
| Yes. Contractor should study CDs, take field measurements. Contractor not responsible for finding errors and omissions |
|
|
Term
According to the A201 Gen. Conditions If contractor find non compliant to codes in CDs
they should |
|
Definition
|
|
Term
| According to the A201 Gen Conditions who is SOLEY responsible for means and methods of construction? |
|
Definition
|
|
Term
| According to the A201 Gen. Conditions what happens if contractor finds concealed or unknown conditions not noted in the CD |
|
Definition
| Contracto shal notify owner/arch witin 21 days of discovery, before such conditions are disturbed |
|
|
Term
| According to the A201 Gen. Conditions If contractor discovers human remains, archeological sites or wetlands not in the cds contractor shall |
|
Definition
Suspend any opperations that may effect them.
Owner to seee gov't authorization to continue. |
|
|
Term
| According to the A201 Gen. Conditions Allowances found in the CD's ? |
|
Definition
| Shall be included in the contract sum |
|
|
Term
| According to the A201 Gen. Conditions Contractor shall hire a _______ superintendent. Arch/owner have ____ days to object to the individual |
|
Definition
|
|
Term
| According to the A201 Gen. Conditions. Contract should submit what to Owner/Architect after being awarded the job? |
|
Definition
Schedule for work
Schedule shall be revised at appropriate intervals |
|
|
Term
| According to the A201 Gen. Conditions Contractor shall maintain a copy of which items? Name 3 |
|
Definition
| Drawings, specs, addenda, change order, other field modification records |
|
|
Term
| According to the A201 Gen. Conditions are submittal part of the Contract Documents? |
|
Definition
| No. are to dmeonstrate eht way by which the contractor intends to conform to CDs |
|
|
Term
| According to the A201 Gen. Conditions By submitting sumittals to architect it represents the contractor has |
|
Definition
| approved them, determined and verified materials, field measurement, and field construction and coordinatied the information |
|
|
Term
Contractor shall
name 3 items |
|
Definition
Confine operation to the project site and not use site for e unreasonsable storage
Contractor shall not cut or alter work completed by owner
contractor shall keep area free from accumulated waste and clean up site upon completion of work
contractor shall provide access to the work in preparation and progress |
|
|
Term
According to the A201 Gen. Conditions
Article 4 Architect
Owner shall retain a ______ architect |
|
Definition
|
|
Term
| According to the A201 Gen. Conditions if Arch is terminated can the contractor object to who is hired to replace? |
|
Definition
| Yes. Contractor to have no objections to new architect |
|
|
Term
| According to the A201 Gen. Conditions When does Contract administration end for Architect? |
|
Definition
| At the date of final certificate of payment |
|
|
Term
| According to the A201 Gen. Conditions Owner and Contractor communicate through |
|
Definition
|
|
Term
| According to the A201 Gen. Conditions Consultants Communicate throug |
|
Definition
|
|
Term
| According to the A201 Gen. Conditions Seperate Contractors shall communicate through |
|
Definition
|
|
Term
| According to the A201 Gen. Conditions Suppliers and sub contractors shall communicate through |
|
Definition
|
|
Term
| According to the A201 Gen. Conditions How does architect certify amounts due to contractor? |
|
Definition
| based on evaluationns of applications for payment and site visits |
|
|
Term
| According to the A201 Gen. Conditions Can the architect reject work or require inspection/testing of work? |
|
Definition
|
|
Term
| According to the A201 Gen. Conditions Who prepares change orders and construction change directives? |
|
Definition
|
|
Term
According to the A201 Gen. Conditions Who will conduct inspection to determin the date of Substantial completion?
And issue certificate of Substantial completion? |
|
Definition
|
|
Term
| According to the A201 Gen. Conditions are the architects descisions on aesthetic effect final? if consistant with the CDs? |
|
Definition
|
|
Term
| According to the A201 Gen. Conditions arch shall respond to RFI in writing within timelimit agreed or reasonable proptness and prepare_____ |
|
Definition
| supplemental drawings as needed |
|
|
Term
Article 5 Subcontractor
After award of the contract, the contractor shall provide a list of ? |
|
Definition
Subcontractors, material suppliers, superintendent, fabricators
Arch/owner has 14 days to object |
|
|
Term
| If contractor defaults. Subs have to? |
|
Definition
| Subs maybe obligated to complere their contract to owner. Subs can ask for more money if more than 30 day for transition of responsibility |
|
|
Term
Article 6 Construction by owner
Owner reserves the right to perform construction of operation related to the project but not the ... |
|
Definition
| Not the work with their own forces. Diffrent project and "the work" |
|
|
Term
Article 7 Change in work
How does a change in work get accomplished |
|
Definition
| Constructino change directive, change order, minor change in work or ASI |
|
|
Term
| Change order requires signiture of |
|
Definition
| Owner, Architect, Contractor |
|
|
Term
| Construction Change directive requires signature of |
|
Definition
|
|
Term
| Minor change in work or Supplimental instrcutions require signiture of |
|
Definition
|
|
Term
| Change order is prepared by |
|
Definition
| architect and signed by owner, arch, contractor |
|
|
Term
| Construction Change Directive (CCD)is prepared by |
|
Definition
| Architect and signed by Owner and Architect |
|
|
Term
| CCD results in chage in price the new price shall be determinded by |
|
Definition
Mutual acceptance of a lump sum
Unit price stated in CD
previously agreed
by cost to be Determined and |
|
|
Term
| If contractor recieves CCD what should they do? |
|
Definition
| Promtly proceed with work determined in CCD |
|
|
Term
| IF conctractor signs CCD indicates |
|
Definition
indicates the contrctors agreement of time/cost and shall be recorded as change order.
If not agreed upon Architect shall determin method of compensation |
|
|
Term
Article 8 Time
Contract time starts and stops when? |
|
Definition
| Starts at date of commencement till substantial completions of the work |
|
|
Term
| Who certifies substantial completion? |
|
Definition
|
|
Term
|
Definition
|
|
Term
| Date of commencement of work and date of Sub complitions are established |
|
Definition
In the agreement.
By exictuting the agreement the contractor is agreeing to the the contract time |
|
|
Term
| Contractor shall not commence work prior to |
|
Definition
|
|
Term
Article 9 Contract Sum
Define Contract sum. |
|
Definition
| Total amount payable by the owner to the contractor for performance of the work per CD's |
|
|
Term
| Define schedule of values |
|
Definition
allocates the contract sum to a various portions of the work
Submitted by contracto before the first application for payment |
|
|
Term
| What is submitted 10 days prior to payment due date |
|
Definition
|
|
Term
| T/F contractor can be paid for material stored off site |
|
Definition
| True if agreed to in advance and location in writing. |
|
|
Term
| Contractor warrants that work covered by an application for payment shall.. |
|
Definition
| transfer title to the owner upon payment |
|
|
Term
| Certificate for payment shall be issuesd within ____ days fo recieving ______ |
|
Definition
| 7 Days of recieving application for payment |
|
|
Term
| Contractor shall pay subs within ____ days of recieving payment |
|
Definition
|
|
Term
| True of false the owner can not request written evidence from contractor the he has paid subs? |
|
Definition
| False. If contractor does not produce within 7 days the owner has right to contact subs directly |
|
|
Term
| What can the contractor due if payment not recieved |
|
Definition
| After 7 days past payment date owner may issue 7 day notice to stop work if not recieved in 7 Days. (14 days min. from missed payment) |
|
|
Term
| When work is sufficiently complete in accordance with the CD it is called |
|
Definition
|
|
Term
| Who prepares the punch list? |
|
Definition
|
|
Term
| What happens at Substantial Completion? |
|
Definition
Warrenty period begins
Owner assumes insurace for building and expences (power/heat etc)
Owner releases retainage |
|
|
Term
| owner may occupy any portion of work at any stage when agreed upon by. Name two |
|
Definition
| Suritey and public authority |
|
|
Term
| Upon final application for payment the architect shall make final inspection. If work is determnined acceptable under the CD's architect issues? |
|
Definition
| Final Certificate of Payment |
|
|
Term
Article 10 Protection of Persons and Property
Who is responsible for site safety |
|
Definition
Contractor
shall take proper safety precausitons and shall provide protection frome damage to: people, the work, the site, adjacent property |
|
|
Term
| If contractor encouunters unknown hazard such as hazardous material they shall |
|
Definition
Stop the work and notify owner in writing.
owner will deal with getting rid of it. Change order may be issued to accommodate cost increase |
|
|
Term
Article 11 insurace and Bond Req's
Contractor needs to carry |
|
Definition
General liability
aut
workers comp
professional liability
performance/payment bond (if required by owner) |
|
|
Term
| Insuracne required by architect |
|
Definition
General Liability
Auto
Work Comp
Professional Liability |
|
|
Term
| Insuracne required by Owner |
|
Definition
Liability Insurance
All risk property insurance
Boiler machinery |
|
|
Term
Article 12 Uncovering and correcting the work
Who pays if arch is required to uncover work for testing? |
|
Definition
If work is not in accordance with CD Contractor pays.
If work is in accordance the owner pays |
|
|
Term
| If faulty work found within one year |
|
Definition
| Contractor fixes. if after a year owner can fix and send bill to the contractor |
|
|
Term
Article 14 Termination by Contractor
After how many days of no payment |
|
Definition
After 30 days of no payment and 7 days written notice.
Or for
Court order
act of government
Payment not made
owner failded to furninsh financial evidence promptly |
|
|
Term
| Termination by Owner with contractor if contractor ? |
|
Definition
Fails to supply skilled workers
fails to pay subs
disregards laws/codes
Owner must supply 7 day notice |
|
|
Term
Termination by Owner for conveniece.
|
|
Definition
| 7 day notice for any reason |
|
|
Term
| What does continuaing contract performance mean |
|
Definition
| all parties shall continue to carry out responsibilities of the contract pending final resolution of claims |
|
|
Term
| Who is the Initial Decision Maker |
|
Definition
The architect
Is required to review claims prior to mediation |
|
|
Term
| Architect may request consultation to help determins solution to claim at ____ expense |
|
Definition
|
|
Term
| Name the 6 steps in the Change Order Process |
|
Definition
1. GC notifies in writing of the proposed change or the owner may also request a change be made
2. Architect commpletes a Proposal Request (AIA 709) detailing the Work
3. contractor submits to Architect response with impact of Cost and time of the proposed work
4. Architect reviews the impact of Cost and Time with the owner
5. if Owner decides not to go ahead with the work. Architect notifies Contractor and nothing more happens
6. if Owner decides to go ahead with the Work, The architect prepares the change order and all three parties sign it |
|
|