Term

22-1. Which of the following is NOT a part of the contract documents?

 

a. addenda

 

b. bid form

 

c. specifications

 

d. owner-contractor agreement

Definition

b. bid form

 

Term

22-2. The owner is protected form incomplete work by the contractor by the use of:

a. indemnification

b. liquidated damages

c. retainage

d. standard contract forms

Definition

d. retainage

 

Term

22-3. The risk for furniture being damaged during shipment is assigned by the:

a. ff&e general conditions

b. owner-designer agreement

c. owner-vender agreement

d. uniform commercial code

Definition

d. uniform commerical code

Term

22-4. If, during construction of a project, the contractor notices that a handrail does not meet the local bldg codes, what action could the designer reasonable expect the contractor to take?

a. notify the designer of the discrepancy in writing

b.correct the situation and submit a change order for the extra work.

c. build the handrail according to the contract documents because conformance to bldg codes is the designer's responsibility

d. notify the designer of the problem and suggest a remedy

Definition

a. notify the designer of the descrepancy in writing

Term

22-5. Which of the following is the interior designer prohibited from doing under terms of the Gener Conditions of the Contract for FF&E?

 

a. prepare change orders and authorize minor changes in the work.

b. determine the date of substantial completion

c.reject work that does not meet the requirements of the drawings.

d. demand that a special inspection be made to determine if the work conforms to the specification

Definition

b. determine the date of substantial completion

Term

22-6. During furniture delivery to the fifth floor of a bldg, elevator transporation is the respondibility of the:

a. bldg mgr

b. FF&E vendor

c. general contractor

d. owner

Definition

d. owner

Term

22-7. Final acceptance of furniture and fixtures is the responsibility of the:

a. architect

b. interior designer

c. the owner

d. vendor

Definition

c. the owner

Term

22-8. Which standard form includes contract information about the owner's right to perform work separate from the main construction contract?

a. instructions to bidders

b. owner-contractor agreement

c. general conditions of the contract

d.supplementary conditions of the contract

Definition

c. general conditions of the contract

Term

22-9. Under what circumstances does the owner have to provide the contractor with evidence of the owner's financial resources to complete the project according to the AIA General Conditions of the Contract for Construction?

a. whenever the contractor asks for such evidence

b. if the project is a public project

c. on request of the contractor if the job is being competitively bid

d. the owner does not have to offer any such proof

Definition

a. whenever the contractor asks for such evidence

Term

22-10. What type of agreement would a designer be advised NOT to work under when doing a residential project?

a. a letter of agreement

b. a series of purchase orders with terms printed on the back

c. a std form of AIA or ASID agreement

 d. a contract prepared by the designer's attorney

Definition

b. a series of purchase orders with terms printed on the back.