Term
| What are the inputs of the 4th process of Project Scope Management? |
|
Definition
1. PMP 2. Project Documents - Scope Statement, Requirements Documentation 3. EEFs 4. OPAs |
|
|
Term
| What are the tools and techniques of the 4th process of Project Scope management? |
|
Definition
1. Expertise 2. Decomposition |
|
|
Term
|
Definition
| Organizing project team work into manageable parts |
|
|
Term
|
Definition
| Lowest level of work where cost and duration can be estimated. |
|
|
Term
| What are the five activities of decomposition? |
|
Definition
| 1. Identify and analyze deliverables/related work 2. Structure WBS 3. Decompose upper WBS 4. Develop and assign identification to WBS components 5. Validate decomposition level is appropriate |
|
|
Term
| What are the outputs of the 4th process of Project Scope management? |
|
Definition
1. Scope Baseline 2. Project Documentation Updates |
|
|
Term
| Describe the Scope Baseline and what it includes |
|
Definition
It is an approved version of the scope statement. 1. Project Scope statement 2. WBS 3. WBS Dictionary |
|
|
Term
| What is a control account? |
|
Definition
| Control point where scope, schedule, and cost are compared to earned value of performance measurements |
|
|
Term
|
Definition
| The functionality of the product |
|
|
Term
| What is the WBS Dictionary? |
|
Definition
| Document detailing information for each WBS element |
|
|